The 11th Street Bridge Park, in partnership with the District Department of Transportation, held a virtual public meeting in 2021. Below, you will find a recording of the meeting and answers to a list of questions from that meeting.
View video recording:
October 6 Bridge Park Q&A Responses
Project Timeline
11th Street Bridge Park Design & Construction Milestones
|
Target Date
|
Develop Bridge Plans, Elevations and Existing and Proposed Sections
|
Aug 2019 – Jan 2020
|
Develop Site Plans (roof, deck, piers, Environmental Education Center)
|
Sept 2019 – Jan 2020
|
Preliminary Plan Design Complete
|
Summer 2020
|
NEPA Process Complete
|
Summer 2020
|
65% Design Complete & Kick off to 100% Design
|
2021
|
Construction drawings complete.
|
August 2022
|
Begin process to solicit general contractor.
|
Fall 2022
|
11th Street Bridge Park Project Team
Architect |
OMA |
Landscape Architect |
OLIN
|
Structural & Geotechnical Engineering |
Whitman, Requardt & Associates
|
35% of projects subcontractors are DC based minority owned firms.
The 11th Street Bridge Park, in partnership with the District Department of Transportation, held a public forum at Anacostia High School in 2019. Below, you will find answers to a list of questions from that meeting.
September 25th Public Meeting Questions & Answers